Before a pavement is placed the surface to be paved must be prepared.
Pavements constructed without adequate surface preparation may not meet
smoothness specifications, may not bond to the existing pavement (in the case of
overlays) or may fail because of inadequate
subgrade support.
Figure 1: Milling Machine
Figure 2: Pavement Sweeping After Milling
Surface preparation generally takes one of two forms:
Anything that can be done to
increase the load-bearing capacity of the subgrade soil will most likely improve
pavement load-bearing capacity and thus, pavement strength and performance.
Additionally, greater subgrade structural capacity can result in thinner (but
not excessively thin) and more economical pavement structures. Finally,
the finished subgrade should meet elevations, grades and slopes specified in the
contract plans.
Generally, subgrade support can be increased by one or several of the
following means:
Compaction. Subgrade should be compacted to adequate density
before pavement placement. If it is not, the subgrade
will continue to compress, deform or erode after construction, causing pavement
cracks and deformation. Generally, adequate density is specified as a
relative density for the top 6 inches of subgrade of not less than 95
percent of the laboratory density determined by ASTM D 698 or D 1557. In
fill areas, subgrade below the top 6 inches is often considered adequate if it
is compacted to 90 percent relative density.
Stabilization. Lime, cement or
emulsified asphalt can be mixed in
with the subgrade soil to increase its strength and stiffness.
Construction geotextiles can be used to help stabilize roadways with early
signs of subgrade failure.
Over-excavation. Poor in situ subgrade
can be replaced with better load-bearing fill. Typically, 1 - 2 ft. of poor soil
may be excavated and replaced with gravel
borrow.
Add a subbase course over the subgrade.
A subbase course offers additional load-bearing capacity. Subbase courses are subjected to the same compaction and elevation requirements as subgrade soils.
After final grading (often called
fine-grading), the subgrade elevation should generally conform
closely to construction plan subgrade elevation. Large elevation discrepancies should not be
compensated for by varying pavement or base thickness because (1) HMA, and
aggregate are more expensive than subgrade and (2) HMA compacts differentially
– thicker areas compact more than thinner areas, which will result in the
subgrade elevation discrepancies affecting final pavement smoothness.
The graded subgrade or the top granular base layer
can be prepared with a prime coat if necessary. A prime coat is a
sprayed application of a cutback
or emulsion
asphalt applied to the surface of untreated subgrade or base layers in order to (Asphalt Institute, 2001):
Fill the surface voids and protect the subbase from weather.
Stabilize the fines and preserve the subbase material.
Promote bonding to the subsequent pavement layers.
Ensure the compacted subgrade is able to support construction traffic. If the subgrade ruts excessively under
construction traffic it should be repaired before being paved over. Left unrepaired, subgrade ruts may
reflectively cause premature pavement rutting and will result in variable
paving thicknesses as the HMA fills the wheel ruts and is displaced by the rut
ridges. The result can be a pavement with areas that are too thin
(over the rut ridges) and too thick (over the rut depressions) instead of a
uniform depth.
Remove all debris, large rocks, vegetation and topsoil from the area to be paved. These items either do not compact well
or cause non-uniform compaction and mat thickness.
Treat the subgrade under the area to be paved with an approved herbicide.
This will prevent or at least retard
future vegetation growth, which could affect subgrade support or lead
directly to pavement failure.
In summary, subgrade preparation should result in a
material (1) capable of supporting loads without excessive
deformation and (2) graded to specified elevations and slopes.
Overlays
make up a large portion of the roadway paving done today. The degree of
surface preparation for an overlay is dependent on the condition and type of the
existing pavement. Generally, the existing pavement should be structurally
sound, level, clean and capable of bonding to the overlay. To meet these
prerequisites, the existing pavement is usually repaired, leveled, cleaned and then coated
with a binding agent.
To maximize an overlay’s useful life, failed sections of the existing
pavements should be patched or replaced and existing pavement cracks should be
filled. If an existing pavement is cracked or provides inadequate
structural support these defects will often reflect through even the
best-constructed overlay and cause premature pavement failure in the form of
cracks and deformations. Small areas
of localized structural failure in the existing pavement should be repaired or
replaced to provide this structural support (see Figures 3 and 4). If the existing
pavement contains areas of inadequate subgrade support, these areas should be removed and the subgrade should be
prepared as
it would be for a new pavement.
Figure 3: Replacing a Deteriorated Portion
of the Existing Pavement
Figure 4: Replacing a Rigid Pavement Slab
Before an HMA Overlay
Existing pavement crack repair methods depend upon
the type and severity of cracks. Badly cracked pavement sections,
especially those with pattern cracking (e.g.,
fatigue cracking) must be
patched or replaced because these distresses are often symptoms of more extensive
pavement or subgrade structural failure (TRB, 2000). Existing cracks other than those symptomatic
of structural failure should be cleaned out (blown out with pressurized air
and/or swept) and filled with a
crack-sealing material
when the cracks are clean and dry (TRB, 2000). Cracks less than
about 0.375 inches in width may be too narrow for crack-sealing
material to enter. These narrow cracks
can be widened with a mechanical router before sealing. If the existing pavement
has an excessive amount of fine cracks but is still structurally adequate, it may be more economical to apply a
general bituminous surface treatment (BST)
or slurry seal instead of filling each individual crack.
A tack coat is a thin bituminous liquid asphalt,
emulsion or
cutback
layer applied between HMA pavement lifts to promote bonding (see Figures 5 and
6). Adequate bonding between construction lifts and especially between
the existing road surface and an overlay is critical in order for the completed
pavement structure to behave as a single unit and provide adequate strength.
If adjacent layers do not bond to one another they essentially behave as
multiple independent thin layers - none of which are designed to accommodate the
anticipated traffic-imposed bending stresses. Inadequate bonding between
layers can result in delamination (debonding) followed by
longitudinal wheel path cracking,
fatigue cracking,
potholes, and other distresses such as
rutting that greatly reduce pavement life (TxDOT, 2001).
The existing pavement should be made as smooth
as possible before being overlaid. It is difficult to make up elevation
differences or smooth out ruts by varying overlay thickness.
HMA tends to
differentially compact; a rule of thumb is that conventional mixes will compact
approximately 0.25 inches per 1 inch of uncompacted thickness
(TRB, 2000). Thus, thicker pavements will compact more. Therefore, before
applying the final surface course the existing pavement is typically
leveled by one or both of the following methods:
Applying a leveling course (Figures 7 and
8). The first lift applied to the existing pavement is used to fill
in ruts and make up elevation differences. The top of this lift, which is relatively smooth, is used as the base
for the wearing course.
Leveling course lifts need to be as thick as the deepest low
spot but not
so thick that they are difficult to compact. Because it is not the
final wearing course, leveling course elevation and grade are sometimes not
tightly specified or controlled. However, contractors and inspectors alike
should pay close attention to leveling course thickness because an excessively
thick leveling course can lead to large overruns in HMA and thus large overruns
in project budget.
Figure 7: Left Side = Leveling Course
Right Side = Leveling + Surface Course
Figure 8: Paving a Leveling
Course
Milling (also called grinding or cold planing). A top layer is milled off the existing pavement to provide a relatively smooth
surface on which to pave. Milling is also commonly used to remove a
distressed surface layer from an existing pavement.
Milling machines are the primary method for removing old HMA pavement
surface material prior to overlay (Roberts et al., 1996). They can be
fitted with automatic grade control to restore both longitudinal and
transverse grade and can remove most existing pavement distortions.
After milling, pavement surfaces should be cleaned off by sweeping or washing (see Figure 2) before any overlay is placed otherwise dirt and dust may decrease
bonding between
the new overlay and the existing pavement. Milling also produces a rough, grooved surface, which will increase the existing
pavement’s surface area when compared to an ungrooved surface. The surface
area increase is dependent on the type, number, condition and spacing of cutting
drum teeth but is typically in the range of 20 to 30 percent, which requires
a corresponding increase in tack coat (20 to 30 percent more) when compared to
an unmilled surface (TRB, 2000). Milling is advantageous because
it:
Efficiently removes
deteriorated pavement that is unsuitable for retention in the overlaid
pavement.
Provides a highly
skid resistant
surface suitable for temporary use by traffic until the final surface can be
placed.
Allows curb and gutter lines to be maintained or reestablished before
HMA
overlays.
Provides an efficient removal technique for material near overhead
structures in order to maintain clearances for bridge structures,
traffic signals and overhead utilities.
Table 1: Milling Machine Parameter Ranges (from
ARRA, 2001)
Specification
Typical Range
Comments
Cut
Width
1.5 inches to 8 feet
(although narrower and wider drums are available)
Drums come in specific widths.Varying widths can be made with multiple passes.
Cut
Depth
up to 10 inches
per pass
It may be easier to make several shallow passes than one deep
pass.
Placing a flexible overlay on a jointed rigid pavement involves some special
considerations. Rigid pavement in Washington State is placed in discrete
slabs, which tend to crack into discrete sections that move as individual
units. Although HMA overlays can accommodate small differential
subgrade movement without cracking, the large differential movement at slab and
crack interfaces is great enough to crack an HMA overlay (called reflection cracking,
one type of which is
joint
reflection cracking).
There are several techniques to prevent (or at least delay the onset of) reflection cracking:
Prevent the slabs or sections from moving by stabilizing the material beneath them.
This involves drilling holes in an unstable PCC slab or section and injecting
an asphaltic or cementitious material to fill any underlying voids. Typically, this method is only an
option for isolated instances of instability. It does not work well
as a general roadway treatment.
Make the overlay structure strong enough to resist cracking. This
usually involves extra granular base layers between the flexible overlay and
the existing rigid pavement or extremely thick flexible layers, both of which
are often not cost effective. Even if these types of preventative
measures are used, they still cannot be guaranteed to prevent reflective
cracking.
Crack/break and seat the underlying rigid pavement. This
involves breaking the underlying rigid pavement into relatively small pieces
(on the order of about 1 ft2
to 2 ft2) by repeatedly dropping a large weight. The pieces
are then seated by 2 to 3 passes of a large rubber tired roller.
Rubblize the underlying rigid pavement. This involves
reducing the underlying rigid pavement to rubble. This rubble is then
used as a high quality base course to support a flexible overlay. Rubblizing is typically done with one of the following two pieces of
equipment:
Resonant pavement breaker (see Figure
8). This equipment strikes the rigid pavement at low
amplitude with a small plate at the resonant
frequency of the slab (usually about 44 Hz) causing the slab to break apart (Roberts et al., 1996). Usually it takes about 14 to
18 passes for a resonant pavement breaker to rubblize an entire 12 ft.
lane (NCAT, 2001).
Multi-head breaker (MHB) (see Figure 9). This
equipment uses a series of independently controlled high amplitude drop hammers to smash the slab.
Typically, there are between 12 and 16 hammers, each weighing between 450 -
680 kg (1000 - 1500 lbs.). Hammers can be dropped from variable
heights (1 - 5 ft.) and cycle at a rate of 30 - 35 impacts per minute. MHBs can rubblize an entire lane (up to 13 ft.) in a single pass
(Antigo Construction, 2001).